POWER

SUBSTITUTION OF SUPERCRITICAL BOILER LINES

Type of ItemSUBSTITUTION OF SUPERCRITICAL BOILER LINES
Final destinationItaly
Year of production2013
ProjectBOILER SUBSTITUTION PLANT
Scope of SupplyDESIGN, SUPPLY, WELDING, TESTING, START UP OF PLANT
NoteDesign, site assembly, welding, and testing of the piping and components for the new attemperation lines. 
Supply, prefabrication and installation of new superheated and reheated attemperation lines of supercritical boiler.
Material: A335 P91, A335 P22.
Testing: Hydraulic Test at 105 bar(g)
.