Type of Item | SUBSTITUTION OF SUPERCRITICAL BOILER LINES |
---|---|
Client | ENEL SPA |
End User | ENEL SPA |
Year of production | 2013 |
Project | BOILER SUBSTITUTION CIVITAVECCHIA PLANT |
Scope of supply | DESIGN, SUPPLY, WELDING, TESTING, START UP OF PLANT |
Note | Design, site assembly, welding, and testing of the piping and components for the new attemperation lines. Supply, prefabrication and installation of new superheated and reheated attemperation lines of supercritical boiler Material: A335 P91, A335 P22 Testing: Hydraulic Test at 105 bar(g) |